To:       RIAC
From:     LOMRC Chairman
Date: 8/5/05
Subject: Greenville Bridge Construction Closure Schedule 8/5 thru 8/19/05
ITCS Memo # 2289

New Greenville Bridge Construction River Closure: For the 2 week period of August 5 2005 thru August 19 2005. The contractor is requesting a river closure of three days on Monday, August 8 from 8:30 A.M. to 4:30 P.M.; Thursday, August 18 from 8:30 A.M. to 4:30 P.M.; and Friday, August 19 from 8:30 A.M. TO 4:30 P.M. Contact vessel on site M/V RAY PENSRUM cell phone 870-265-0433.

RIBB Homepage  Previous Page


Last updated: Friday, 05-Aug-2005 12:03:59 MDT