To:       RIAC
From:     LOMRC Chairman
Date: 8/19/05
Subject: New Greenville Bridge Construction River Closure 8/19/05 thru 9/2/05
ITCS Memo # 2296

New Greenville Bridge Construction River Closure: For the 2 week period of August 19, 2005 thru September 2, 2005. The contractor is requesting a river closure of three (3) days. Contact vessel on site M/V RAY PENSRUM cell phone 870-265-0433.

Here is the schedule for the next 2 weeks for bridge closures on the New Greenville Bridge:
All closures run from 8:30 a.m. to 4:30 p.m.
23 Aug: Tuesday: 8:30 a.m. to 4:30 p.m.
30 Aug: Tuesday: 8:30 a.m. to 4:30 p.m.
31 Aug: Wednesday: 8:30 a.m. to 4:30 p.m.
Note: the projected closure that I mentioned last week for 26 Aug has been cancelled.