To:       RIAC
From:     LOMRC Chairman
Date: 10/21/05
Subject: Greenville Bridge Construction Closure 10/21/05 thru 11/4/05
ITCS Memo # 2307

New Greenville Bridge Construction River Closure: For the 2 week period of October 21, 2005 thru November 4, 2005. The contractor is requesting a river closure of five (5) days. Contact vessel on site M/V RAY PENSRUM cell phone 870-265-0433.

Here is the schedule for the next 2 weeks for bridge closures on the New Greenville Bridge:
24 Oct: Monday
25 Oct: Tuesday
28 Oct: Friday
31 Oct: Monday
03 Nov: Thursday
All closures are set for 8:30 a.m. to 4:30 p.m.