To:       RIAC
From:     LOMRC Chairman
Date: 11/23/05
Subject: New Greenville Bridge Construction Closure 11/25 thru 12/9/05
ITCS Memo # 2318

New Greenville Bridge Construction River Closure: For the 2 week period of November 25, 2005 thru December 9, 2005. The contractor is requesting a river closure of four (4) days. Contact vessel on site M/V RAY PENSRUM cell phone 870-265-0433.

Here is the schedule for the next 2 weeks for bridge closures on the New Greenville Bridge:
28 Nov: Monday
01 Dec: Thursday
05 Dec: Monday
09 Dec: Friday
All closures are set for 8:30 a.m. to 4:30 p.m.