To:       RIAC
From:     LOMRC Chairman
Date: 12/19/05
Subject: New Greenville Bridge Construction Closures 12/16 thru 12/31/05
ITCS Memo # 2331

New Greenville Bridge Construction River Closure: For the 2 week period of December 16, 2005 thru December 31, 2005. The contractor is requesting a river closure of four (4) days. Contact vessel on site M/V RAY PENSRUM cell phone 870-265-0433.

Here is the schedule for the next 2 weeks for bridge closures on the New Greenville Bridge:
19 Dec: Monday
22 Dec: Thursday
28 Dec: Wednesday
31 Dec: Saturday
All closures are set for 8:30 a.m. to 4:30 p.m.


RIBB Homepage  Previous Page


Last updated: Monday, 19-Dec-2005 07:07:07 MST
© 2001 Virtual Data Systesm.