To:       RIAC
From:     RIAC Chairman
Date: 3/30/08
Subject: Lock #25 Update 3/30/08
ITCS Memo # 2645


All
Plan on having a conference call at 1000 Monday March 31st. I will provide the numbers in the morning.

-----Original Message-----
From: Schimpf, Andrew C MVS [mailto:Andrew.C.Schimpf@usace.army.mil]
Sent: Sunday, March 30, 2008 6:24 PM
To: Henleben, Ed
Cc: DellOrco, Lou MVS; Dooley, Alan J MVS; Allensworth, H K MVS; Stringham, George E MVS; Dalrymple, Nicole M MVS
Subject: Lock 25 Closure Update - 30 March


Ed,

Update on progress at Lock 25.

The heavy rains last night and this morning slowed progress. At this point we still plan to re-open the lock Monday evening. Today the crew completed fabrication of the new secondary anchorage pin. The day shift will work over to complete assembly of the secondary gate anchorage which had to be sent to the Service Base last night to be turned. It will be shipped back to the site tonight. The night shift will complete the boring of the embedded anchorage c-channel, and the top and bottom doubler plates. Tomorrow the team will install secondary anchorage into gudgeon and set anchorage pin. Once the gate is hung it will have to be adjusted to seal at quoin and miter, and the walkway re-installed. As I said, at this point we are still planning to complete repair tomorrow evening. The critical path to complete will be simultaneous completion of the boring (weather may slow) and completion of secondary anchor assembly.

Andy Schimpf, P.E.
Rivers Project Manager
US Army Corps of Engineers
St. Louis District
301 Riverlands Way
West Alton, Mo. 63386-1704
(636) 899-2600 ext. 225 (office)
(636) 899-0044 (office direct)
(636) 899-2655 (fax)
(314) 630-6280 (mobile)
email: andrew.c.schimpf@usace.army.mil